And Now the Time Is Near… Project Closure: The Forgotten Finale
The last weld is inspected. The system is commissioned. The plant hums to life. The project team moves on. And somewhere, months later, the “as-built” documentation trickles in.
This is the reality of project closure in capital-intensive
industries. It’s not a clean finish. It’s a slow fade. And in that fade, vital
information is lost.
As-Built Files:
Late, Light, and Lacking
By the time the general mechanical contractor delivers the
final documentation, the project is already in operation. The team that built
it? Long gone. The team that runs it? Often unaware of what’s missing.
And what’s missing is more than just equipment manuals. It’s
the full technical backbone of the asset:
- Specification
sheets
- Design
calculations
- Relief
scenarios
- Control
narratives
- Commissioning
reports
- Warranty
conditions
These aren’t just nice-to-haves. They’re essential for safe,
efficient, and compliant operations. Yet 10 years down the line, try finding
the relief valve sizing basis or the original heat exchanger spec. It’s like
chasing ghosts. As-built documentation is critical for long-term maintenance
and compliance, as highlighted in this
guide from BusinessesHubs.
The “Well Maintenance File” Is a Myth Without Closure
Operations and maintenance teams need a single source of
truth. But too often, they inherit a patchwork of PDFs, spreadsheets, and
tribal knowledge. The “well maintenance file”, the one that should contain
everything, is either incomplete or nonexistent.
This leads to:
- Reactive
maintenance
- Costly
troubleshooting
- Compliance
risks
- Redundant
engineering work
And it’s all preventable. Asset integrity depends on
capturing and preserving technical decisions, as emphasized in GPA
Canada's Asset Integrity presentation.
Closure Is a Discipline, Not a Deadline
We must treat project closure as a formal phase, not an
afterthought. That means:
- Assigning
dedicated resources for documentation validation
- Ensuring
full scope: not just equipment, but engineering intent
- Digitizing
and integrating into CMMS and asset platforms
- Hosting
structured handover sessions with O&M teams
- Creating
searchable, durable repositories—not just folders on someone’s desktop
Best practices for project closeout are well-documented,
such as in AIA’s
construction contract closeout guide and ProjectManager’s
closure checklist.
When Should Closure Begin? At the Beginning.
Closure isn’t something you “do at the end.” It must be
scheduled from day one. The same way we plan for procurement, commissioning,
and startup, we must plan for closure. That means:
- Including
closure milestones in the project schedule
- Budgeting
time and resources for documentation and handover
- Defining
ownership: who collects, who validates, who delivers
- Aligning
with operations early to understand what they need
If closure isn’t planned up front, it becomes a scramble.
And when it’s a scramble, things fall through the cracks.
Where Does the Information Go?
Not into a USB stick. Not buried in a SharePoint folder. It
must go into systems that operations actually use:
- CMMS
(Computerized Maintenance Management Systems)
- BIM
(Building Information Modeling) platforms
- Asset
performance dashboards
- Document
control systems with long-term retention
The goal is not just to store information but to make it
accessible, searchable, and usable for the next 20 years.
AN real life example Refinery Expansion Project –
Lost Relief Scenarios and Costly Rework
A major refinery in North America underwent a multi-year
expansion to increase throughput and integrate new desulfurization units. The
project was technically successful, commissioning went smoothly, and production
targets were met. But the closure phase? Practically nonexistent.
- The
as-built documentation was delivered six months after startup and only
included equipment manuals and P&IDs.
- Relief
valve sizing calculations and scenario documentation were never
transferred to the operations team.
- Control
narratives were stored in a contractor’s private folder and never migrated
to the plant’s document control system.
- The
specification sheets for critical rotating equipment were missing, making
it impossible to validate spare parts or maintenance intervals.
Years later, during a turnaround, the plant needed to verify
relief loads for a new flare header tie-in. But the original basis for the
relief scenarios was nowhere to be found. Engineers had to reverse-engineer the
entire system, costing weeks of effort and delaying the turnaround schedule.
The Cost of Neglect
- $2.5
million in engineering rework
- 3-week
delay in turnaround completion
- Lost
production valued at $8 million
- Regulatory
scrutiny due to incomplete safety documentation
This wasn’t a failure of design or construction—it was a
failure of transition. The project team had moved on, and no one was assigned
to validate and integrate the final documentation. Closure was treated as a
formality, not a deliverable.
Lessons Learned
This case underscores the need to:
- Schedule
closure activities from day one, not after commissioning
- Assign
dedicated resources for documentation validation and handover
- Include
engineering intent—not just drawings—in the final package
- Ensure
integration into CMMS, DCS, and document control systems
- Host
formal handover sessions with operations and reliability teams
Closure isn’t just about wrapping up. It’s about ensuring
continuity, safety, and long-term performance. Without it, even world-class
projects can become operational headaches.
Let’s Close the Gap
Project closure is the bridge between construction and
operation. If we don’t build it properly, we leave future teams stranded. Let’s
stop treating it as a formality. Let’s make it a milestone worth executing with
precision.
Because the end of a project isn’t the end of its story.
It’s the beginning of its legacy.
#ProjectClosure #EngineeringLifecycle #AssetIntegrity
#MaintenanceMatters #AsBuiltDrawings #ReliefScenarios #TriplePointEngineering
#dickverhoeven

Comments
Post a Comment