The CapEx Conundrum: Navigating the Inconsistent Phases of Project Engineering
The world of Capital Expenditure (CapEx) projects, whether building a new petrochemical plant, expanding a mine, or constructing a massive data center, relies on a rigid, phased approach to manage risk and investment. These projects are high, stakes endeavors, often costing billions and spanning years. Their success hinges entirely on one foundational principle: Front, End Loading (FEL).
However, the terminology used to define these crucial early
phases; FEL 1, FEL 2, FEL 3, pre, FEED, FEED, Basic Engineering, and Detailed
Engineering; is notoriously inconsistent. This lack of standardization is more
than a semantic annoyance; it is a major source of project failure, leading to
scope creep, budget overruns, and severe schedule delays.
This detailed guide will decode these phases, explain the
dangerous ambiguities, and introduce the most critical rule for all project
managers and owners: The Engineering Work Done Test.
Decoding the CapEx Project Phases and AACE
Classifications
CapEx projects are fundamentally sequential; each phase acts
as a funnel, reducing uncertainty and increasing cost commitment. The industry
generally follows the Front, End Loading (FEL) concept, which defines the level
of project definition before the major capital outlay.
To introduce structure to the financial side, we often
reference the AACE International Cost Estimate Classifications. These classes
directly correlate with the engineering phase, reflecting the accuracy range of
the cost estimate:
1. Concept / Feasibility Phase
- Common
Acronyms/Alternatives: FEL 1 (Front, End Loading 1), Define,
Opportunity Identification
- AACE
Estimate Class: Class 5
- Accuracy
Range:
- Typical
Focus/Deliverables: High, level business case, market analysis, technology
screening, initial capacity. The goal is a formal Go/No, Go decision
point on viability.
2. Conceptual Engineering Phase
- Common
Acronyms/Alternatives: FEL 2, Pre, Project Planning, pre, FEED
- AACE
Estimate Class: Class 4
- Accuracy
Range:
- Typical
Focus/Deliverables: Select preferred concept, preliminary PFDs (Process
Flow Diagrams), site selection, major equipment list started, rough
plot plan, and initial regulatory reviews.
3. Front, End Engineering Design Phase (The Critical
Gate)
- Common
Acronyms/Alternatives: FEL 3, FEED
- AACE
Estimate Class: Class 3 () to
Class 2 ()
- Accuracy
Range:
- Typical
Focus/Deliverables: Defines major equipment specifications, P&IDs
(Piping & Instrumentation Diagrams) initiated, detailed plot plan,
extensive scope definition, and formal scope freeze. This package
is the basis for the Final Investment Decision (FID) and the subsequent
EPC bid.
4. Basic Engineering Phase
- Common
Acronyms/Alternatives: Often synonymous with FEED (particularly in
Europe/Asia).
- AACE
Estimate Class: Class 2
- Accuracy
Range:
- Typical
Focus/Deliverables: If separate from FEED, this phase further
develops process details, prepares complete mechanical and electrical
specifications, and is sometimes focused purely on preparing the
Invitation to Bid (ITB) package for procurement of long, lead items.
5. Detailed Engineering Phase
- Common
Acronyms/Alternatives: DE
- AACE
Estimate Class: Class 1
- Accuracy
Range:
- Typical
Focus/Deliverables: Production of all necessary construction drawings
(isometrics, electrical layouts, civil designs), full vendor data
integration, procurement specifications finalized, and final Issued For
Construction (IFC) documents. The project is ready for physical execution.
The Terminology Trap: Where Words Fail Projects
The confusion arises because project teams often use these
terms interchangeably or locally redefine them, leading to misalignment between
the owner, the engineering contractor (EPC), and third, party licensors.
1. FEL, vs. FEED: A Regional Split
In many North American organizations, FEL 3 is the
formal name for the final gate review that precedes project sanction and the
commencement of physical construction or major procurement. Critically, the
deliverables required for FEL 3 are functionally identical to what the
rest of the world refers to as the FEED package. Both terms signify the
point where the project scope is frozen, the process design is complete, and
the estimate is accurate enough for a Final Investment Decision (FID).
If a company uses both terms, ensure the deliverables for each are not
redundant or or, worse, incomplete.
2. The Ambiguity of Basic Engineering
Basic Engineering is arguably the most ambiguous
phase. There are two primary definitions:
- Definition
A (EU/Asia): Basic Engineering is the FEED. It covers the
fundamental process design, heat and mass balances, PFDs, and initial
P&IDs necessary to define the overall plant structure.
- Definition
B (A Bridge Phase): Basic Engineering is the phase that follows the frozen
FEED package, but precedes full Detailed Engineering. In
this context, it takes the high, level process specifications from FEED
and generates the detailed mechanical, civil, and electrical
specifications needed for procurement of long, lead items, but stops short
of creating every last isometric and cable schedule required for
construction.
If your project is global, a contract stating "Basic
Engineering" without a precise checklist of deliverables (e.g., P&IDs
90% issued for design, equipment data sheets 100% complete) is a recipe for
scope disputes.
3. pre, FEED and Its Misuse
The term pre, FEED is often used to describe the work
done during the FEL 2 phase. It’s essential to view pre, FEED as selection
work. It takes multiple viable concepts identified in FEL 1, narrows
them down through preliminary engineering calculations, and selects the single,
optimal path forward. The primary danger here is skipping this phase. Moving
straight from an FEL 1 concept (AACE Class 5) into a full FEED
(aiming for Class 2) guarantees substantial rework and cost waste because too
many fundamental choices are being made under the pressure of detailed design.
The "Engineering Work Done" Test: A Key Differentiator
The maxim serves as the ultimate firewall against the most
common project affliction: Schedule, Driven Engineering (SDE).
A key principle of successful CapEx execution is this:
The engineering work actually done determines where you are in the process, not
the schedule or a wish.
The Danger of Schedule, Driven Engineering (SDE)
SDE occurs when project teams prioritize hitting an
arbitrary phase completion date on the Gantt chart over completing the
prerequisite deliverables. When a gate review is rushed, critical uncertainties
are passed downstream. The team may claim, for instance, that FEED is
complete on June 1st because the schedule dictates it, even if the following
conditions are true:
- The HAZOP
(Hazard and Operability Study) revealed 20 high, priority action items
that require P&ID revisions.
- Final
long, lead equipment vendor data has not been integrated into the
P&IDs or equipment layout.
- The
final geotechnical survey data hasn't been used to confirm the foundation
design philosophy.
In this scenario, the project has not completed FEED.
It has simply started Detailed Engineering (DE) under the delusion of
completion. Every incomplete task passed from FEED into DE forces
highly paid DE engineers to stop designing and start solving overdue
process problems, escalating costs exponentially.
The True Test: Deliverable, Driven Engineering (DDE)
The only antidote to SDE is Deliverable, Driven
Engineering (DDE). Project success is measured by the quality and
completeness of the engineering package transferred to the next phase, not by
the calendar date.
Here is an extended breakdown of what the "Engineering
Work Done Test" demands at the most critical transition point: The move
from FEED/FEL 3 to Detailed Engineering (DE):
1. Scope Freeze and Change Control
- Test:
Is the scope (including capacities, turndown rates, and key design
philosophy documents) formally frozen, signed off by all stakeholders
(owner, operations, engineering), and governed by a rigorous change
control procedure?
- Failure
Consequence: If not, minor changes requested by Operations during DE
can trigger chain reactions across P&IDs, equipment specs, and plot
plans, resulting in thousands of hours of rework and budget erosion.
2. Estimate and Procurement Reconciliation
- Test:
Is the Class 2 estimate based on reconciled data? Has the project team
moved past factoring based on Class 3 data and instead integrated firm or
budgetary quotes for all major and long, lead equipment (e.g., reactors,
compressors, main columns)?
- Failure
Consequence: An unreconciled estimate leads to financial surprise. The
goal of FEED is to ensure the FID (Final Investment Decision)
is based on reality, not optimism. If actual vendor pricing differs from
the estimate, the scope may have to be cut mid, DE, leading to
massive engineering waste.
3. P&ID Finalization
- Test:
Are the Piping and Instrumentation Diagrams (P&IDs) issued as
"Approved for Design" (AFD) or "Issued for
Construction" (IFC) with no remaining open process hold points? Has
the HAZOP been completed and all necessary P&ID revisions
incorporated?
- Failure
Consequence: The P&IDs are the Bible of the plant. If they are in flux
during DE, every piping isometric, every instrument list, and every
electrical load calculation is potentially wrong. This is the single
largest source of rework.
4. Interface Management and Site Readiness
- Test:
Are all major interfaces (e.g., utility tie, in points, external
pipelines, existing plant connections) defined, and have the adjacent
owners formally accepted the interface boundaries? Is the geotechnical and
topographical survey work fully complete and incorporated into the civil
design basis?
- Failure
Consequence: Assuming tie, in points or site conditions often results in
schedule catastrophe during construction when a necessary piece of
existing infrastructure is found to be incompatible or non, existent.
5. The "Readiness to Bid" Check
- Test:
For projects using an EPC contractor, is the engineering package
sufficiently robust to allow multiple contractors to bid on an
apples, to, apples basis without having to perform their own expensive
upfront engineering?
- Failure
Consequence: A poor FEED package forces EPC bidders to add
massive risk contingency (inflating the price) or forces them to perform
hidden, unfunded engineering, which they will inevitably cut corners on
once the contract is awarded.
The "Engineering Work Done Test" should be treated
like a pilot's pre, flight checklist. No matter how late the flight is, you do
not take off until every item is verified. A project does not proceed until
every prerequisite deliverable is complete.
Why Robust Phase Definition is a Financial Imperative
The entire structure of phased project delivery is designed
to capitalize on the Wedge of Influence. In the early phases (FEL 1
and FEL 2), the ability of the team to influence the project's cost and
operational characteristics is highest, while the actual money spent is lowest.
Conversely, during Detailed Engineering and Construction, the
majority of the budget is spent, but the ability to make high, impact, low,
cost changes is almost zero.
Poorly defined gates force decision, making into the high, cost, low, influence zone. By rigorously enforcing the DDE model and demanding clear answers to the "Engineering Work Done Test," organizations can significantly reduce budget risk and increase the predictability of their CapEx returns.
References & Resources:
- Construction
Industry Institute (CII): The industry leader in defining Front,
End Loading (FEL) best practices and quantifying the benefits of
robust project definition.
- AACE
International (Association for the Advancement of Cost Engineering):
Provides the definitive framework for cost estimate classification, which
is essential for aligning financial accuracy with engineering progress.
- Project
Management Institute (PMI): Offers foundational knowledge on phase
gating and project governance.
This framework for project phasing and the critical emphasis
on completed deliverables underscore the enduring truth of CapEx
execution: time spent planning is rarely wasted. Defining your phases
clearly and enforcing the engineering standards ensures your project moves from
wish to reality with financial control and technical integrity.
Need Help:
TriplePoint.Engineering
can help navigate these waters and define the clarity you need.
#CapEx #ProjectManagement #EngineeringDesign #FEED #FEL
#BasicEngineering #EPC #ProjectDelivery #OilandGas #ProjectControls
#triplepointengineering #dickverhoeven


Comments
Post a Comment